![]()
January 2026
The Old Main renovation project continues to advance across all floors. In the basement, Mechanical, Electrical, Plumbing, and Fire Protection (MEPF) overhead work is nearing completion at 85%, and ramp construction for the seating area of the auditorium is in progress. On the first floor, wall framing is almost finished, with MEPF in‑wall rough‑ins about halfway complete. The second floor has moved into insulation and drywall work, while the third floor is seeing paint applied to walls and open ceilings. Painting to wrapping up on the fourth floor, and bathroom tile installation is complete. Millwork is about to begin. Exterior work is also progressing steadily, with the new lobby vestibule taking shape.
Click here to see the January 2026 update.




![]()



