Old Main Monthly Update.jpg

Click to see the November 2025 update.

lower level theater november 2025.jpg

Basement: Structural upgrades are complete in the lower level, and the theater build-out has begun. (November 2025)

first floor november 2025.jpg

First Floor: Structural upgrades are 90% complete. Some MEPF (Mechanical, Electrical, Plumbing, and Fire Protection) overhead installation has begun.

third floor november 2025.jpg

Third Floor: Framing is complete. Overhead MEPF installation is complete, and in-wall MEPF installation is 85% complete.

mezzanine november 2025.jpg

Fourth floor: The brick facade on both the east and west additions is 60% complete. Skylights are installed, and the roof system is 90% complete.

blog divider.jpg

Click to see the September 2025 update.

Click to See the August 2025 update.

Click to See the July 2025 update.

Click to see the June 2025 update.

Click to see the May 2025 update.

Click to see the April 2025 update.

See the March 2025 update.

See January/February 2025 update.

See December 2024 update.

See November 2024 update.

See October 2024 update.

See September 2024 update.

Renovation Photos September 2025

east addition.jpg

East addition stairwell progress, with CMU work complete and crews installing the mechanical room. (September 2025)

north wall.jpg

The north wall section removed has been filled with CMU blocks, and facade brick will be added to match the existing exterior. (September 2025)

basement looking up.jpg

View from the basement level looking up into the west mechanical room addition. (September 2025)

subgrade.jpg

Progress on subgrade preparations for the northeast parking lot. (September 2025)

blog divider.jpg