Old Main Monthly Update.jpg

Click to see the December 2025 update.

west addition 12-02-2025.jpg

Exterior: Brick installation continues on the east and west additions. (December 2025)

theater 12-02-2025.jpg

BASEMENT: Theater HVAC and ceiling installation are underway. (December 2025)

third floor 12-02-2025.jpg

THIRD FLOOR: In-wall MEFP (Mechanical, Electrical, Plumbing, and Fire protection) installation is 98% complete and drywall will begin soon. (December 2025)

fourth floor 12-02-2025.jpg

FOURTH FLOOR: Drywall installation, taping, and painting are underway. (December 2025)

blog divider.jpg

Click to see the November 2025 update.

Click to see the September 2025 update.

Click to See the August 2025 update.

Click to See the July 2025 update.

Click to see the June 2025 update.

Click to see the May 2025 update.

Click to see the April 2025 update.

See the March 2025 update.

See January/February 2025 update.

See December 2024 update.

See November 2024 update.

See October 2024 update.

See September 2024 update.

Renovation Photos November 2025

lower level theater november 2025.jpg

Basement: Structural upgrades are complete in the lower level, and the theater build-out has begun. (November 2025)

first floor november 2025.jpg

First Floor: Structural upgrades are 90% complete. Some MEPF (Mechanical, Electrical, Plumbing, and Fire Protection) overhead installation has begun. (November 2025)

third floor november 2025.jpg

Third Floor: Framing is complete. Overhead MEPF installation is complete, and in-wall MEPF installation is 85% complete. (November 2025)

mezzanine november 2025.jpg

Fourth floor: The brick facade on both the east and west additions is 60% complete. Skylights are installed, and the roof system is 90% complete. (November 2025)

blog divider.jpg